← e-tugra cases
Bugzilla #1659426 Audit Delay

E-Tugra: audit delay due to COVID-19/environmental disaster restrictions

RESOLVED FIXED e-tugra
This summary was auto-generated by AI and revised by me when needed — accuracy improves with each update. Always refer to the official Bugzilla thread as the authoritative source. If you spot an inaccuracy, let me know via the contact form.
AI Summary

This case concerns E-Tugra’s delay in completing its next CA audit. E-Tugra stated it became aware of the problem on 20 July and that it planned to start the next audit with its auditor on 17 August, but could not schedule it due to lockdown restrictions related to an environmental disaster/pandemic. E-Tugra reported that the last audit covered 3 August 2018 through 26 July 2019, and that the next audit was originally planned to start before 20 July with audit reports sent by 15 October, but COVID-19 and local restrictions caused postponement. E-Tugra explained that curfew and suspended international flights affected planning and physical access, and that it could not plan the audit before 26 July; it later stated that the audit start was missed again on 17 August due to the auditor’s workload and other plans. E-Tugra said it and LSTI (the auditing company) were working to complete the audit in September and discussed the possibility of partial or full remote auditing. The audit was later completed between 21–25 September by LSTI, and E-Tugra stated it would finalize the audit report and audit letter and announce when ready. The bug is marked RESOLVED with resolution FIXED.

Model: gpt-5.4-nano Generated: 2026-06-13 21:20 UTC Revised: 2026-06-16 18:34 UTC Confidence: 0.86 5 comments
Chronology
  1. E-Tugra reported becoming aware of the audit timing problem and planned a next audit start on 17 August.
  2. E-Tugra stated it could not start the scheduled audit with the auditor due to COVID-19 lockdown restrictions.
  3. LSTI completed E-Tugra’s 2020 yearly audit between 21–25 September.
Thread Activity
  1. E-Tugra — Davut Tokgöz explained that E-Tugra could not schedule the next audit for 17 August due to lockdown/pandemic restrictions and said audits were postponed to September, with reports to follow.
  2. Community commenter — Ryan Sleevi asked for more precise details and referenced Mozilla’s CA audit delay expectations documentation.
  3. E-Tugra — Davut Tokgöz provided context on COVID-19 impacts in Turkey and LSTI’s planning constraints, and said the audit completion was being worked toward in September, including possible remote auditing.
  4. E-Tugra — Davut Tokgöz stated the 2020 yearly audit was completed between Sep 21–25 by LSTI and that E-Tugra would announce when the audit report and letter were ready.
Participants
E-Tugra Community commenter
Similar Local Cases
#1669518 RESOLVED Audit Document Audit Delay Opened 2020-10-06 · Closed 2024-06-30 · 67% similar
PKIoverheid: Overdue audit statements for intermediate certificates
#1724530 RESOLVED Ca Documents Audit Delay Opened 2021-08-06 · Closed 2024-06-30 · 59% similar
Microsoft PKI Services: Overdue Audit Reports 2021
#1695993 RESOLVED Ca Documents Audit Delay Opened 2021-03-02 · Closed 2024-06-30 · 57% similar
SECOM: Outdated audit statements for intermediate certificates
#2031062 UNCONFIRMED Audit Delay Opened 2026-04-11 Still Open · 57% similar
Sri Lanka CERT – Audit Statement Delay Explanation Letter
#1507862 RESOLVED Audit Delay Opened 2018-11-16 · Closed 2023-02-22 · 57% similar
ACCV: Late Audit Statement
#1649507 RESOLVED Ccadb Bug Audit Delay Opened 2020-06-30 · Closed 2024-06-30 · 47% similar
Network Solutions: Audit report delay
#1566586 RESOLVED Audit Delay Opened 2019-07-16 · Closed 2023-02-22 · 45% similar
Asseco DS / Certum: Overdue Audit Statements 2019
#1462797 RESOLVED Certificate Misissuance Opened 2018-05-18 · Closed 2023-02-22 · 41% similar
E-Tugra: Improper DER results in failure to comply with RFC 5280 - Invalid characters in PrintableString